华星东方承建的湖南省邵阳市武冈生活垃圾焚烧发电项目烟气净化工程于2024年09月02日通过72+24小时试运行。
The flue gas cleaning project of Wugang household waste incineration power generation plant in Shaoyang, Hunan Province, undertaken by our company, has passed the trial operation of 72-hour + 24- hour since 2nd. Sep, 2024.
该项目设计规模日焚烧处理垃圾500吨,配置1x500t/d焚烧炉+1×14MW汽轮发电机组。烟气净化采用“SNCR(非本次合同范围内)+半干法(旋转雾化半干反应塔)+干法(喷射消石灰)+活性炭喷射+袋式除尘器”的烟气净化工艺,为我司设备供货工程
The designing capacity of the project is 500 tons of waste incineration per day equipped with 1x500t/d incinerator +1×14MW steam turbine generator set. The flue gas cleaning process of "SNCR (exclude the scope of the contract) + semi-dry method (rotating atomized semi-dry reactor) + dry method (spray slaking lime) + activated carbon spray + bag dust collector", all of which will be achieved by our company’s equipments.
华星东方在湖南省的业绩涵盖包括:常德二期、三期、常德石门、邵阳、邵阳武冈、衡阳、衡阳常宁等多个项目。
Huaxing East’s references in Hunan Province includes: Phase II & Phase III in Changde, Shimen Changde, Shaoyang, Wugang Shaoyang, Hengyang, Changning Hengyang and many other projects.
评论